Installation of New Parcel Freight System
Duration: 2 Weeks to Complete
Overview
Arrive onsite to assess the job requirements and determine when the client site is available to start the project and the deadline for completion.
Proceed to get a Safe Work Method Statement (SWMS) together for WHS requirements. Once approved, prepare the site for installation; barricade off the work area, prepare a laydown area for tools and equipment, ready for the installation.
Receive shipments of conveyor equipment and check that all items have arrived as per the order. Assemble and install all equipment, making any modifications required onsite.
The team worked closely with electrical trades to ensure consistent flow of installation. Once installed mechanically and electrically, the system was commissioned and handed over to the customer. Then monitored through a full cycle to ensure everything was working to customer standards.
Parcel Freight System
- Telescopic conveyor
- Belt under roller conveyor
- Belt over deck conveyor
- Belt under roller carousel
Client Requirements
- Tight deadline 2 weeks
- Work in a live warehouse environment
- SWMS & WHS
- System commissioned to customer’s Standards
Services Provided
- Project management
- Onsite supervision
- Modifying and fitting equipment
- Mechanical assembly and installation of the conveyor system
- Commission of the system to customer
- Service agreement with the customer
- Breakdown service maintenance program
Outcome
Despite some unforeseen challenges at the beginning stages of the project, the parcel freight system was successfully installed before deadline and is fully operational to customer standards.
For more information, get in touch.
Mulley Industries Pty Ltd
15 Springcreek Road Mt Hunter, NSW 2570
ABN: 44 136 474 881
Greg Mulley
Managing Director
m: 0414 512 396
e: [email protected]